2020
|
Teamed up with Chia Cheng Construction Co., Ltd. For Slipforming works of Datan Combined Cycle Power Plant Expansion Project- Units 8 & 9 Chimney EPC Project.
|
2016
|
Teamed up with Chia Cheng Construction Co., Ltd. for the slip-forming of the new control tower at Taoyuan International Airport.
|
2012
|
Undertook EPC chimney & fly ash silos works for Talin Power Plant Renovation Project in conjunction with Chia Cheng Construction Co., Ltd. for CTCI Corporation.
|
2011
|
Expanded to the Vietnamese market by undertaking Formosa Ha Tinh Steel Corporation Son Duong Port harbor craft basin and wharf construction project.
|
2005
|
Teamed up with Tractebel Gas Engineering to undertake 2x80,000 M3 ethylene & propylene refrigerated storage tanks EPC project for Formosa Petrochemical Co. in Ningbo, China.
|
2004
|
Constructed 3x80,000M3 ethylene & propylene refrigerated storage tanks for Formosa Petrochemical Corporation at Mailiao, Taiwan.
Undertook Hsinchu county stadium EPC project.
|
2001
|
Undertook Taipei Harbor Wharves E13, E14 & E15 Project for Formosa Petrochemical Corporation.
Undertook Taichung Fossil Power Plant units #9-10 chimney project for Taiwan Power Company.
|
1999
|
Applied prestressed slipform method on large-diameter LPG refrigerated storage tanks (φ77M).
|
1998
|
Awarded “1998 Excellence in Automation” by Taiwan Construction Research Institute.
|
1996
|
Awarded “1995 Excellence in Construction” by Ministry of the Interior.
Certified under ISO 9002 Quality Management System by DNV.
Established PT. Ting Tai Konstruksi Indonesia.
|
1995
|
Established Ting Tai Construction Singapore Pet.
Undertook cement silo project at Asia Cement’s Pulau Damar Laut terminal.
Awarded “Excellence in Construction” from Ministry of Economic Affairs and “Premier Quality Construction” from The Executive Yuan for Taiwan Power Company Taichung Fossil Power Plant Units 5~8 Project.
|
1994
|
Completely self-performed 250m chimney EPC project..
Established Jakarta, Indonesia, branch office.
Undertook expansions of the Jakarta and Surabaya plants for PT.
Bogasari Flour Mills, (total capacities up to 727,180 tons).
|
1993
|
Developed capability to lift 600t, ∮6.7m, 250m steel chimney liners.
Developed nickel alloy liner welding capability for chimney projects.
|
1992
|
Successfully integrated RC slipform method with steel structure assembly to construction the preheater tower for Asia Cement Corp.’s Hualien Plant. Ting Tai received a silver medal for Application of Automation in Construction Works from the Minitry of the Interior.
Undertook the EPC project of Pali Sewage Treatment Plant using egg-shaped digester forms from RSB of Austria and prestressing system from Vorspann-Technik of Austria.
|
1991
|
Undertook a 60,000t grain silo project at Taichung Harbor, Taiwan.
|
1989
|
Completed the RC chimney for Taiwan’s first refuse incineration plant.
|
1986
|
Completed the first domestically slipformed 138m RC chimney in Taiwan.
|
1985
|
Undertook Taiwan’s largest parking tower project at the time.
|
1984
|
First successful application of the slipform method to non-circular structure in Taiwan.
Combination of prestressing with slipform to strengthen RC structures.
|
1983
|
Advanced to simultaneous slipform of 12 units of ∮10m silos.
|
1982
|
Set foot in overseas market by undertaking Phases 6-8 cement plants of PT.
Indocement and grain silos PT. Bogasari Flour Mills in Indonesia.
|
1981
|
Successfully transferred variable cross-section conical slipforming technology to Taiwan.
|
1980
|
Achieved simultaneous slipforming of 10 units of ∮8.5m silos.
|
1978
|
Technical cooperation with Gleschnellbau GmbH of Germany, to introduce conical slipforming technique to Taiwan.
|
1977
|
Applied automatic hydraulic system, instead of manual lifting, to slipform construction of caissons.
|
1976
|
Ting Tai Construction Co., Ltd. established and registered as a Class A general contractor.
|